Development applications in Burwood

Every development application lodged with Burwood Council and published to the NSW Planning Portal, from lodgement through to occupation certificate.

Applications lodged
1,052
Total value
$2.6 billion
New dwellings
5,295
Determined
891
Last 12 months
144
Median determination
79 days
Search Burwood applications

How long does a DA take in Burwood?

Half of determined applications in Burwood were decided within 79 days of lodgement, with a mean of 122 days across 868 determined applications. The mean sits above the median because a small number of long-running applications pull it up.

The NSW median across councils with comparable volume is 46 days, so Burwood determines applications slower than the state's middle. Determination time varies widely by development type and by how complete the lodgement is.

What is in the record

Devlens links the four NSW registers into one timeline per site: development applications (DA), complying development certificates (CDC), construction certificates (CC) and occupation certificates (OC). That means you can see not just what was approved in Burwood, but what was actually built and when it was occupied.

Each record carries the address, applicant-declared cost of works, dwelling count, status, lodgement and determination dates, and a map position. The register is refreshed from the NSW Planning Portal every night.