Development applications in Kiama

Every development application lodged with The Council of the Municipality of Kiama and published to the NSW Planning Portal, from lodgement through to occupation certificate.

Applications lodged
1,702
Total value
$909 million
New dwellings
1,713
Determined
1,488
Last 12 months
264
Median determination
77 days
Search Kiama applications

How long does a DA take in Kiama?

Half of determined applications in Kiama were decided within 77 days of lodgement, with a mean of 99 days across 1,464 determined applications. The mean sits above the median because a small number of long-running applications pull it up.

The NSW median across councils with comparable volume is 46 days, so Kiama determines applications slower than the state's middle. Determination time varies widely by development type and by how complete the lodgement is.

What is in the record

Devlens links the four NSW registers into one timeline per site: development applications (DA), complying development certificates (CDC), construction certificates (CC) and occupation certificates (OC). That means you can see not just what was approved in Kiama, but what was actually built and when it was occupied.

Each record carries the address, applicant-declared cost of works, dwelling count, status, lodgement and determination dates, and a map position. The register is refreshed from the NSW Planning Portal every night.