Development applications in Mid-Western

Every development application lodged with Mid-Western Regional Council and published to the NSW Planning Portal, from lodgement through to occupation certificate.

Applications lodged
2,020
Total value
$601 million
New dwellings
1,978
Determined
1,750
Last 12 months
350
Median determination
55 days
Search Mid-Western applications

How long does a DA take in Mid-Western?

Half of determined applications in Mid-Western were decided within 55 days of lodgement, with a mean of 86 days across 1,736 determined applications. The mean sits above the median because a small number of long-running applications pull it up.

The NSW median across councils with comparable volume is 46 days, so Mid-Western determines applications slower than the state's middle. Determination time varies widely by development type and by how complete the lodgement is.

What is in the record

Devlens links the four NSW registers into one timeline per site: development applications (DA), complying development certificates (CDC), construction certificates (CC) and occupation certificates (OC). That means you can see not just what was approved in Mid-Western, but what was actually built and when it was occupied.

Each record carries the address, applicant-declared cost of works, dwelling count, status, lodgement and determination dates, and a map position. The register is refreshed from the NSW Planning Portal every night.