Development applications in Warrumbungle
Every development application lodged with Warrumbungle Shire Council and published to the NSW Planning Portal, from lodgement through to occupation certificate.
- Applications lodged
- 310
- Total value
- $107 million
- New dwellings
- 163
- Determined
- 275
- Last 12 months
- 76
- Median determination
- 69 days
How long does a DA take in Warrumbungle?
Half of determined applications in Warrumbungle were decided within 69 days of lodgement, with a mean of 92 days across 273 determined applications. The mean sits above the median because a small number of long-running applications pull it up.
The NSW median across councils with comparable volume is 46 days, so Warrumbungle determines applications slower than the state's middle. Determination time varies widely by development type and by how complete the lodgement is.
What is in the record
Devlens links the four NSW registers into one timeline per site: development applications (DA), complying development certificates (CDC), construction certificates (CC) and occupation certificates (OC). That means you can see not just what was approved in Warrumbungle, but what was actually built and when it was occupied.
Each record carries the address, applicant-declared cost of works, dwelling count, status, lodgement and determination dates, and a map position. The register is refreshed from the NSW Planning Portal every night.
Open the Warrumbungle registerOther NSW councils
- Central Coast development applications
- Lake Macquarie development applications
- Northern Beaches development applications
- Sydney development applications
- Blacktown development applications
- The Hills development applications
- Sutherland development applications
- Wollongong development applications
- Inner West development applications
- Shoalhaven development applications
- Newcastle development applications
- Camden development applications
- Canterbury-Bankstown development applications
- Wollondilly development applications
- Maitland development applications
- Cessnock development applications
- Liverpool development applications
- Port Macquarie-Hastings development applications
- Coffs Harbour development applications
- Parramatta development applications
- Mid-Coast development applications
- Penrith development applications
- Cumberland development applications
- Woollahra development applications